How much will your home cost?
Example Estimate
| Budget Item | Est. Cost |
| 01 Land | |
| 01.02 Property Tax | 0.00 |
| 01.03 Association Dues | 0.00 |
| 02.01 Purchase | 0.00 |
| Total 01 Land | 0.00 |
| 02 Plans and Permits | |
| 02.01 Plans | 0.00 |
| 02.02 Building Permits | 4,799.68 |
| 02.03 City License | 0.00 |
| 02.04 Sewer Permit | 0.00 |
| 02.05 Builder’s Risk Insurance | 0.00 |
| 02.06 Soil Test | 650.00 |
| 02.07 ADEM Permit | 0.00 |
| 02.08 Impact Fee | 0.00 |
| 02.09 Termite Treatment | 0.00 |
| Total 02 Plans and Permits | 5,449.68 |
| 03 Utilities | |
| 03.01 Electricity | 1,834.37 |
| 03.02 Water | 2,451.15 |
| 03.03 Portable Toilet | 1,380.00 |
| 03.04 Gas | 6,881.74 |
| Total 03 Utilities | 12,547.26 |
| 04 Site Work | |
| 04.01 Survey | 1,300.00 |
| 04.02 Lot Clearing | 0.00 |
| 04.03 Survey Stakeout | 1,900.00 |
| Total 04 Site Work | 3,200.00 |
| 05 Foundation | |
| 05.01 Foundation Material | 2,378.05 |
| 05.02 Foundation Labor | 5,238.70 |
| 05.03 Concrete for Footing | 6,182.48 |
| 05.04 Pump Truck for Footing | 0.00 |
| 05.05 Block Material | 6,315.11 |
| 05.06 Block Labor | 6,109.50 |
| 05.07 Fill for Slab | 13,125.00 |
| 05.08 Concrete for Slab | 8,000.60 |
| 05.09 Pump Truck for Slab | 0.00 |
| 05.10 Concrete for Wall | 0.00 |
| 05.11 Pump Truck for Wall | 1,400.00 |
| 05.12 Backfill Material | 0.00 |
| 05.13 Backfill Labor | 110.00 |
| 05.14 Waterproofing | 0.00 |
| 05.15 Pilings | 0.00 |
| 05.16 Piling Labor | 0.00 |
| 05.17 Footing Labor | 4,499.00 |
| 05.18 Block Fill Labor | 0.00 |
| 05.19 Storm Door | 1,416.81 |
| Total 05 Foundation | 54,775.25 |
| 06 Framing | |
| 06.01 Framing Material | 54,177.84 |
| 06.02 Framing Labor | 30,226.45 |
| Total 06 Framing | 84,404.29 |
| 07 Windows | 22,741.09 |
| 08 Exterior Doors | 7,107.02 |
| 09 Roof | |
| 09.01 Roof Material | 10,585.97 |
| 09.02 Roof Labor | 3,091.49 |
| 09.03 Copper | 0.00 |
| 09.04 Metal | 0.00 |
| Total 09 Roof | 13,677.46 |
| 10 Siding | |
| 10.01 Brick Material | 24,205.66 |
| 10.02 Brick Labor | 26,150.00 |
| 10.03 Stucco | 0.00 |
| 10.04 Hardie Siding Material | 23,244.33 |
| 10.05 Hardie Siding Labor | 6,000.00 |
| 10.06 Stone Material | 0.00 |
| 10.07 Stone Labor | 0.00 |
| 10.08 Hardie Cornice Material | 0.00 |
| 10.09 Hardie Cornice Labor | 14,000.00 |
| 10.10 Vinyl Cornice | 0.00 |
| 10.11 Vinyl Siding | 0.00 |
| 10.12 Exterior Paint | 6,759.50 |
| Total 10 Siding | 100,359.49 |
| 11 Exterior Trim & Decks | |
| 11.01 Vinyl Trim | 0.00 |
| 11.02 Trim Other | 3,319.87 |
| 11.03 Gutters | 12,500.73 |
| 11.04 Deck Materials | 0.00 |
| 11.05 Deck Labor | 0.00 |
| 11.06 Porch Screen | 0.00 |
| 11.07 Porch Ceiling Material | 1,401.42 |
| 11.07 Porch Ceiling Labor | 5,000.00 |
| Total 11 Exterior Trim & Decks | 22,222.02 |
| 12 Plumbing | |
| 12.01 Plumbing L&M | 28,140.00 |
| 12.02 Plumbing Fixtures | 21,488.27 |
| 12.03 Jacuzzi | 0.00 |
| 12.04 Bath Accessories | 0.00 |
| 12.05 Sewer Line | 0.00 |
| 12.06 Grinder Pump | 0.00 |
| 12.07 Septic System | 0.00 |
| Total 12 Plumbing | 49,628.27 |
| 13 HVAC | 32,598.00 |
| 14 Electrical | |
| 14.01 Electrical L&M | 56,781.30 |
| 14.02 Lights | 11,306.07 |
| 14.03 Generator | 0.00 |
| Total 14 Electrical | 68,087.37 |
| 16 Specialty | |
| 16.01 Structured Wire | 0.00 |
| 16.02 Security | 0.00 |
| 16.03 Intercom | 0.00 |
| 16.04 Central Vacuum | 0.00 |
| 16.05 Stereo | 0.00 |
| Total 16 Specialty | 0.00 |
| 17 Fireplace | 11,350.00 |
| 18 Insulation | 11,860.00 |
| 19 Sheetrock | |
| 19.01 Sheetrock Material | 7,676.79 |
| 19.02 Sheetrock Labor | 7,939.46 |
| Total 19 Sheetrock | 15,616.25 |
| 20 Interior Doors | 9,990.83 |
| 21 Millwork & Trim | |
| 21.01 Trim Material | 19,742.94 |
| 21.02 Trim Labor | 48,340.00 |
| 21.03 Door Knobs | 0.00 |
| 21.04 Stair Parts | 2,324.12 |
| 21.05 Closet Shelves | 0.00 |
| 21.06 Mirrors | 0.00 |
| 21.07 Mantle | 0.00 |
| 21.08 Shower Door | 4,555.68 |
| 21.09 Porch Rails & Columns | 5,981.63 |
| 21.10 Blinds | 0.00 |
| Total 21 Millwork & Trim | 80,944.37 |
| 22 Cabinets & Vanities | 54,530.31 |
| 23 Garage Doors | 6,232.00 |
| 24 Paint | 15,591.20 |
| 27 Counter Tops | 14,781.00 |
| 32 Appliances | 24,872.68 |
| 33 Flooring | 45,034.79 |
| 34 Cleanup | 6,000.00 |
| 35 Landscaping | |
| 35.01 Landscaping | 60,427.00 |
| 35.02 Sprinkler System | 0.00 |
| 35.03 Mailbox | 0.00 |
| 35.04 Sod | 0.00 |
| 35.05 Fence | 0.00 |
| Total 35 Landscaping | 60,427.00 |
| 36 Driveway | |
| 36.01 Driveway Material | 14,460.50 |
| 36.02 Driveway Labor | 6,907.00 |
| Total 36 Driveway | 21,367.50 |
| 37 Steps | 0.00 |
| 39 Finance | |
| 39.01 Closing Cost | 0.00 |
| 39.02 Interest | 0.00 |
| Total 39 Finance | 0.00 |
| 40 Sales Commission | 0.00 |
| 41 Miscellaneous | 0.00 |
| Construction Total | 855,395.13 |
| Builder Fee | 150,952.08 |
| TOTAL | 1,006,347.21 |