How much will your home cost?

Example Estimate

Budget Item Est. Cost
01 Land
01.02 Property Tax 0.00
01.03 Association Dues 0.00
02.01 Purchase 0.00
Total 01 Land 0.00
02 Plans and Permits
02.01 Plans 0.00
02.02 Building Permits 4,799.68
02.03 City License 0.00
02.04 Sewer Permit 0.00
02.05 Builder’s Risk Insurance 0.00
02.06 Soil Test 650.00
02.07 ADEM Permit 0.00
02.08 Impact Fee 0.00
02.09 Termite Treatment 0.00
Total 02 Plans and Permits 5,449.68
03 Utilities
03.01 Electricity 1,834.37
03.02 Water 2,451.15
03.03 Portable Toilet 1,380.00
03.04 Gas 6,881.74
Total 03 Utilities 12,547.26
04 Site Work
04.01 Survey 1,300.00
04.02 Lot Clearing 0.00
04.03 Survey Stakeout 1,900.00
Total 04 Site Work 3,200.00
05 Foundation
05.01 Foundation Material 2,378.05
05.02 Foundation Labor 5,238.70
05.03 Concrete for Footing 6,182.48
05.04 Pump Truck for Footing 0.00
05.05 Block Material 6,315.11
05.06 Block Labor 6,109.50
05.07 Fill for Slab 13,125.00
05.08 Concrete for Slab 8,000.60
05.09 Pump Truck for Slab 0.00
05.10 Concrete for Wall 0.00
05.11 Pump Truck for Wall 1,400.00
05.12 Backfill Material 0.00
05.13 Backfill Labor 110.00
05.14 Waterproofing 0.00
05.15 Pilings 0.00
05.16 Piling Labor 0.00
05.17 Footing Labor 4,499.00
05.18 Block Fill Labor 0.00
05.19 Storm Door 1,416.81
Total 05 Foundation 54,775.25
06 Framing
06.01 Framing Material 54,177.84
06.02 Framing Labor 30,226.45
Total 06 Framing 84,404.29
07 Windows 22,741.09
08 Exterior Doors 7,107.02
09 Roof
09.01 Roof Material 10,585.97
09.02 Roof Labor 3,091.49
09.03 Copper 0.00
09.04 Metal 0.00
Total 09 Roof 13,677.46
10 Siding
10.01 Brick Material 24,205.66
10.02 Brick Labor 26,150.00
10.03 Stucco 0.00
10.04 Hardie Siding Material 23,244.33
10.05 Hardie Siding Labor 6,000.00
10.06 Stone Material 0.00
10.07 Stone Labor 0.00
10.08 Hardie Cornice Material 0.00
10.09 Hardie Cornice Labor 14,000.00
10.10 Vinyl Cornice 0.00
10.11 Vinyl Siding 0.00
10.12 Exterior Paint 6,759.50
Total 10 Siding 100,359.49
11 Exterior Trim & Decks
11.01 Vinyl Trim 0.00
11.02 Trim Other 3,319.87
11.03 Gutters 12,500.73
11.04 Deck Materials 0.00
11.05 Deck Labor 0.00
11.06 Porch Screen 0.00
11.07 Porch Ceiling Material 1,401.42
11.07 Porch Ceiling Labor 5,000.00
Total 11 Exterior Trim & Decks 22,222.02
12 Plumbing
12.01 Plumbing L&M 28,140.00
12.02 Plumbing Fixtures 21,488.27
12.03 Jacuzzi 0.00
12.04 Bath Accessories 0.00
12.05 Sewer Line 0.00
12.06 Grinder Pump 0.00
12.07 Septic System 0.00
Total 12 Plumbing 49,628.27
13 HVAC 32,598.00
14 Electrical
14.01 Electrical L&M 56,781.30
14.02 Lights 11,306.07
14.03 Generator 0.00
Total 14 Electrical 68,087.37
16 Specialty
16.01 Structured Wire 0.00
16.02 Security 0.00
16.03 Intercom 0.00
16.04 Central Vacuum 0.00
16.05 Stereo 0.00
Total 16 Specialty 0.00
17 Fireplace 11,350.00
18 Insulation 11,860.00
19 Sheetrock
19.01 Sheetrock Material 7,676.79
19.02 Sheetrock Labor 7,939.46
Total 19 Sheetrock 15,616.25
20 Interior Doors 9,990.83
21 Millwork & Trim
21.01 Trim Material 19,742.94
21.02 Trim Labor 48,340.00
21.03 Door Knobs 0.00
21.04 Stair Parts 2,324.12
21.05 Closet Shelves 0.00
21.06 Mirrors 0.00
21.07 Mantle 0.00
21.08 Shower Door 4,555.68
21.09 Porch Rails & Columns 5,981.63
21.10 Blinds 0.00
Total 21 Millwork & Trim 80,944.37
22 Cabinets & Vanities 54,530.31
23 Garage Doors 6,232.00
24 Paint 15,591.20
27 Counter Tops 14,781.00
32 Appliances 24,872.68
33 Flooring 45,034.79
34 Cleanup 6,000.00
35 Landscaping
35.01 Landscaping 60,427.00
35.02 Sprinkler System 0.00
35.03 Mailbox 0.00
35.04 Sod 0.00
35.05 Fence 0.00
Total 35 Landscaping 60,427.00
36 Driveway
36.01 Driveway Material 14,460.50
36.02 Driveway Labor 6,907.00
Total 36 Driveway 21,367.50
37 Steps 0.00
39 Finance
39.01 Closing Cost 0.00
39.02 Interest 0.00
Total 39 Finance 0.00
40 Sales Commission 0.00
41 Miscellaneous 0.00
Construction Total 855,395.13
Builder Fee 150,952.08
TOTAL 1,006,347.21